Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

A project is considered approved once Ministry of Education and Child Care funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.

  • The completion/occupancy dates in this report are target dates only and subject to change as the projects proceed.
  • This progress chart is updated following each board meeting.
  • It is best to view this website from a desktop or laptop. Otherwise you can use the scroll bar at the bottom of the pages.

 


Logo





SiteDescription
Approval
Design
Tender
Award
Construction
Completion*
Projected Student Occupancy

207 Ta'talu Elem

27-Classroom
New School
Apr 6, 2020
Design Complete
Awarded
92%
Oct 2024

118 South Meridian Elem

8-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
58%
May 2025

161 Semiahmoo Trail Elem

10-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
44%
May 2025

115 Snokomish Elem

27-Classroom
New School
Mar 30, 2021
Design Complete
Awarded
26%
March 2026
16-Classroom 
Prefabricated Addition
Sep 27, 2023
Design Complete
Awarded
10%
Fall 2024

12-Classroom
Prefabricated Addition

Sep 27, 2023
Design Complete
Awarded
15%
Fall 2024
152 Walnut Road Elem
4-Classroom (additional)
Prefabricated Addition

June 20, 2024In processIn process 0%Fall 2025
8-Classroom
Prefabricated Addition
Sep 27, 2023
Design Complete
Awarded
15%
Fall 2024

20-Classroom
Addition

Jan 10, 2023
In process
Spring 2025
0%
Fall 2027
18-Classroom
Addition
May 26, 2023
In process
Fall 2025
0%
Spring 2028

23-Classroom
Addition

May 9, 2023
In process
Fall 2025
0%
Spring 2028

BUILDING ENVELOPE PROJECTS

022 Queen Elizabeth Sec
BEP
Approved
In process



150 Tamanawis Sec
BEP
Approved
In process



174 Kirkbride ElemBEPPending



162 Bayridge ElemBEPPending



028 North Surrey SecBEPPending



131 Hyland ElemBEPPending










SUPPORTED PROJECTS - Pending Ministry Funding Approval

20-Classroom
Addition
Pending




20-Classroom
Addition
Pending




8-Classroom
Addition
Pending




37-Classroom
New School
Pending




20-Classroom
Addition
Pending




6-Classroom
Prefabricated Addition
Pending




Old Yale Road Elem
10-Classroom
Prefabricated Addition
Pending




*This column represents the percentage of contract value paid out to the contractor.

Design Stage
Following approval of the funding agreement with the Ministry of Education, the design stage begins. Sketch plans/schematic designs are the preliminary design concept. The sketch plan then advances to a more detailed design, used to secure City of Surrey development/building permits. These designs are included in the bid tender package.

Tender Stage
When a project's design is complete it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage
After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors affecting the time required to finish a project.

Occupancy Stage
In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.