果冻传媒

Skip to main content

Completed Projects

[ Current Projects Completed Projects | Future Projects ]

Completed Projects

maddaugh-road-elementary-rendering.60849664577.png

  • Address:
  • Date of Approval: Ministry of Education approval March 18, 2017
  • Expansion: up to 200-seat Addition (approx. 8 classrooms)
  • Student Occupancy: September 2018

  • Address:
  • Date of Approval: Ministry of Education approval October 23, 2014
  • Expansion: up to 1500-seat Capacity
  • Student Occupancy: September 2018

  • Address: 6248 144 St, Surrey, BC V3X 1A1
  • Date of Approval: Ministry of Education approval July 10, 2018
  • Expansion: up to 700-seat Addition (approx. 28 classrooms)
  • Student Occupancy: September 2018

  • Address:
  • Date of Approval: Ministry of Education approval October 2017
  • Student Occupancy: September 2018

  • Address:
  • Date of Approval: Ministry of Education approval August 2017
  • Student Occupancy: November 2018

  • Address:
  • Date of Approval: Ministry of Education approval March 18, 2017
  • Expansion: 200-seat addition, (approx. 8 classrooms)
  • Student Occupancy: September 2019

Pacific Heights Elementary Addition (site 134)

  • Address:
  • Date of Approval: Ministry of Education approval December 4, 2017
  • Expansion: up to 300-seat Addition (approx. 12 classrooms)
  • Student Occupancy: April 2020

  • Address: 
  • Date of Approval: Ministry of Education approval April 30, 2018
  • Expansion: 150 new seats (approx. 6 classrooms)
  • Student Occupancy: September 2020

  • Address:
  • Date of Approval: Ministry of Education revised budget approval December 6, 2018
  • Expansion: up to 605-seat Capacity (approx. 25 classrooms)
  • Student Occupancy: November 2020

  • Address:
  • Date of Approval: Ministry of Education revised budget approval December 6, 2018
  • Expansion: up to 605-seat Capacity (approx. 25 classrooms)
  • Student Occupancy: January 2021

Coyote Creek Elementary Addition (site 157)

  • Address:
  • Date of Approval: Ministry of Education approval April 30, 2018
  • Expansion: 100 new seats (approx. 4 classrooms)
  • Tender: Bid 21-168-006 Awarded to Mierau Contractors Ltd. May 2019
  • Student Occupancy: February 2021

Maddaugh Elementary New School (site 184)

  • Address: 
  • Date of Approval: Ministry of Education approval October 7, 2016
  • Expansion: 605 new seats (approx. 25 classrooms)
  • Tender: Bid 18-168-044 Awarded to Pro-Can Construction Group Corp. Dec 2018
  • Student Occupancy: March 2021

Sullivan Elementary Addition (site 021)

  • Address:
  • Date of Approval: Ministry of Education approval March 18, 2017
  • Expansion: 200 new seats (approx. 8 classrooms)
  • Tender: Bid 19-168-004 Awarded to Clark Builders June 2019
  • Student Occupancy: September 2021

Grandview Heights Secondary New School (site 177)

  • Address: 
  • Date of Approval: Ministry of Education approval October 10, 2016
  • Expansion: 1500 new seats (approx. 59 classrooms)
  • Current Phase: Construction Closeout
  • Tender: Bid 19-168-001 Awarded to Yellowridge Construction Ltd. April 2019
  • Tender: Bid 19-168-008 Awarded to S.McKay Construction May 2019
  • Student Occupancy: September 2021

George Greenaway Elementary Seismic Upgrade (site 090)

  • Address: 
  • Date of Approval: Ministry of Education approval August 27, 2019
  • Student Occupancy: April 2022

Holly Elementary Seismic Upgrade (site 081)

  • Address:
  • Date of Approval: Ministry of Education approval August 27, 2019
  • Student Occupancy: April 2022

Prince Charles Elementary Seismic Upgrade (site 044)

  • Address:
  • Date of Approval: Ministry of Education approval April 23, 2020
  • Student Occupancy: May 2022

Queen Elizabeth Secondary Seismic Upgrade (site 022)

  • Address:
  • Date of Approval: Ministry of Education approval July 15, 2020
  • Student Occupancy: September 2022

Regent Road Elementary New School (site 218)

  • Address: 
  • Date of Approval: Ministry of Education approval August 9, 2017
  • Expansion: 655 new seats (approx. 27 classrooms)
  • Student Occupancy: September 2022

  • Address:
  • Date of Approval: Ministry of Education approval February 11, 2020
  • Expansion: 250 new seats (approx. 10 classrooms)
  • Student Occupancy: November 2022

Morgan Elementary Addition (site 188)

  • Address:
  • Date of Approval: Ministry of Education approval June 3, 2020
  • Expansion: 190 new seats (approx. 8 classrooms)
  • Student Occupancy: February 2023

White Rock Elementary Addition (site 009)

  • Address:  
  • Date of Approval: Ministry of Education approval April 20, 2020
  • Expansion: 195 new seats (approx. 8 classrooms)
  • Student Occupancy: March 2023

  • Address:
  • Date of Approval: Ministry of Education approval June 8, 2020
  • Expansion: 195 new seats (approx. 8 classrooms)
  • Student Occupancy: September 2023



image description
Back to top